News Flash

News Releases

Posted on: June 28, 2022

TXDOT Project Will Rebuild Highway 385 from 8th St. to 42nd St.

TXDOT will begin a new project to rehabilitate and resurface U.S. Highway 385 in Odessa on July 6th.

A project to rehabilitate and resurface a 2.3-mile segment of U.S. Highway 385 in Odessa is scheduled to begin the week of July 6. Work will stretch from Highway 191 (42nd Street) to Eighth Street. 

To minimize impact on traffic on this major traffic corridor through town, some of the intersection work will be done at night. 

The work scheduled for the first eight phases of the project will be from 8 p.m. to 6 a.m. The following work locations will be done Sunday night through Thursday night.

>> The two outside lanes from 38th Street to 42nd Street, followed by the three inside lanes in the same area.

>> The two outside lanes on the north side of the intersection at University Boulevard, followed by the outside lanes on the south side of the same intersection. This will include tie-ins transitions to University Boulevard.

>> The three inside lanes of the entire intersection at University Boulevard.

>> The two outside lanes on the south side of the intersection at Eighth Street, followed by the outside lanes on the north side of the same intersection. This will include tie-ins to Eighth Street.

>> The three inside lanes of the entire intersection at Eighth Street.

After the night work is completed in the above-mentioned areas, daytime work will be done to finish the project. The daytime work will take place in these locations:

>> The two outside lanes between Eighth Street and 23rd Street, followed by work on the three inside lanes.

>> The two outside lanes between 23rd Street and University Boulevard, followed by work on the three inside lanes.

>> The two outside lanes between University Boulevard and 42nd Street, followed by work on the three inside lanes.

After those phases are complete, a final surface will be placed on the entire project. 

The project also calls for new traffic signals to be installed at 31st Street and for pedestrian signals to be placed at 18th Street, which is just north of where Highway 385 splits (Grant Avenue splits and becomes what is known locally as Kermit Highway and Andrews Highway). Minor signal improvements will also be placed at 17th Street and 38th Street.

Concrete work will replace curbs, gutters, sidewalks, driveways, and ramps throughout the project limits at different times.

Motorists are reminded that state law requires them to obey warning signs in a construction area. It is very possible that extra law enforcement will be present in the work zones at various times.

The project is scheduled to take approximately 15 months to complete.

Jones Brothers Dirt & Paving Contractors Inc. of Odessa won the project with a low bid of a little more than $6.75 million.

For more information, contact Gene Powell at gene.powell@txdot.gov or call (432) 498-4746.

Facebook Twitter Email

Other News in News Releases

Keeping You Informed

Posted on: May 26, 2023
Working for You

Working for YOU

Posted on: April 10, 2023
Holiday Trash Schedule

Holiday Trash Schedule

Posted on: April 4, 2023
Water Conservation Challenge

Mayor's Water Conservation Challenge

Posted on: April 4, 2023
Working for You

Working for YOU!

Posted on: March 31, 2023
Martin Marquez

Downtown Odessa's Egg Hunt

Posted on: March 30, 2023

Keep Odessa Beautiful

Posted on: March 28, 2023

We are hiring!

Posted on: March 24, 2023

Working for You!

Posted on: March 23, 2023

Water Line Replacement Project

Posted on: March 17, 2023

March Sales Tax Check

Posted on: March 8, 2023

Faudree Road Construction Traffic Update

Posted on: January 20, 2023

Tanglewood Lane Reconstruction Project

Posted on: December 30, 2022

August Sales Tax Check

Posted on: August 19, 2022

Faudree Road Updates

Posted on: April 7, 2022

No Cost COVID-19 PCR Tests

Posted on: November 28, 2021